Somerville Schools · School Committee Meeting
Clogged Roof Drain Flooded West Somerville School Classrooms
West Somerville Neighborhood School · School Committee · Nov 12, 2026
Rain got into third-floor classrooms at the West Somerville Neighborhood School during roof work in October, closing the school for a day, city and school officials told the School Committee on Oct 19.
- What happened: roofers worked over the Indigenous Peoples' Day weekend. Rain on Sunday night, Oct 11, came in around a roof drain. A camera later showed the drain pipe was clogged, said Richard Raiche, the city's infrastructure director.
- Damage: water ruined drywall, which crews cut out to head off mold. School was closed Oct 13, and both first grades moved to the library.
- Who pays: not settled. The roofing contractor has denied fault and plans to bill for the extra work, Raiche said. The city will review the claim.
- The roof: the part over the classrooms is finished. Raiche expected most remaining work done by the end of October, with small fixes into November.
- Other schools: the same thing could happen elsewhere, Raiche said. Roofs at the Healey and Kennedy schools are next in line. On Oct 22 the City Council asked for a report on this roof and a review of roof drains at all schools.
- Makeup day: on Nov 2 the School Committee added a noon-dismissal school day at the school on Jan 4, 2027, to make up for Oct 13.
Sources: School Committee meeting video, Nov 2, 2026 (calendar vote) · City Council minutes, Oct 22, 2026 (items 26-1555 and 26-1529) · School Committee meeting video, Oct 19, 2026 (roof report from 37:00)